Thursday, July 7, 2016

Transportation and Construction Project Updates in Tigard


Summer PavingSummer paving work is in progress, with the major paving work beginning this week.  Signs have been posted and cards sent to notify the public of upcoming construction.  This summer’s tentative paving schedule (weather permitting) is:

Street
Begin/End Location
Paving Dates
Paving Time
72nd Avenue
Hwy 99W to 260 feet south of Hwy 99W
July 18 – 22
Night
72nd Avenue
Beveland Rd to Hwy 217 northbound ramps
July 19 – 22
Night
72nd Avenue
Upper Boones Ferry Rd to Bridgeport Village
July 25–Aug 4
Night
78th Avenue
Pfaffle St to Hwy 99W
July 17 – 21
Night
121st Avenue
Ann St to Tippitt St
July 8 – 15
Day
Dartmouth Street
Hwy 99W to Atlanta St (Costco)
July 17 – 21
Night
Hunziker Street
72nd Ave to 7585 Hunziker
July 20 – 22
Night
Landmark Lane
72nd Ave to end of street
July 24 – 28
Night
Locust Street
Hall Blvd to Greenburg Rd
July 7 – 14
Day
Oak Street
69th Ave to 71st Ave
July 6 – 8
Day
Sandburg Street
End of street to 72nd Ave
July 21 – 27
Night
Ventura Court
Alfred St to Barbara Ln
July 5 – 8
Day
Walnut Street
116th Ave to 122nd Ave
July 8 - 15
Day

Busier streets and nonresidential streets will be paved at night to avoid traffic and business disruption (note: work is not planned on Friday and Saturday nights).  Striping and replacement of traffic signal loops, speed bumps, etc. will be done a couple of weeks after paving.  Call the project information line at 503-718-2760 or Mike McCarthy at 503-718-2462 with questions, comments, or concerns.
 
Note, regarding work at Walnut Street (Tiedeman to 116th and intersection with 135th)
Walnut Street is under construction between 116th and Tiedeman to add sidewalks, bike lanes, a center turn lane, replacement water line, and underground utilities, and install a traffic signal in place of the all-way-stop at the intersection of Walnut St with 135th Ave.  Construction work is scheduled through Summer 2017, with a three-week closure from July 25 through August 15, 2016 to replace the culvert west of the Fowler tennis courts.  More information can be found on the city's construction update page.
 

 

Thursday, June 2, 2016

Residents Weigh in on Tigard’s Neighborhoods

In late April and early May, the City of Tigard repeated its 2013 Neighborhood Network survey, to see how our residents’ views have changed over time. All told, 88 residents participated in the online questionnaire asking how residents felt about where they lived, their neighbors and issues that mattered close to home. We shared the survey through the 14 neighborhood network blogs and the city’s social media.

Overall, residents spoke favorably of where they lived. Their concerns focused on traffic, the need for additional sidewalks, street lights and more. Residents’ ability to walk safely in their neighborhoods and traffic safety concerns stood out. Survey goers also talked about ways they could build better connections with their neighbors. Participants listed parks and trails, the library and a sense of community as valuable local amenities.

Please see the survey questionnaire results and summary of comments for more information.

FROM THE SURVEY:

1) Overall, would you say that you are satisfied or dissatisfied with your neighborhood as a place to live?



2) In general, would you say that the neighborhood is improving, stable or declining?

Wednesday, May 11, 2016

Public Works Day on May 15, Fun for the Family

Everyone is invited to the City of Tigard's celebration of Public Works Day. Bring the family and learn how the city manages some of your most important assets.

  • Sunday, May 15, 9 a.m. to 2 p.m.
  • Public Works Building  (8777 SW Burnham St., Tigard)
  • Free, outdoor event, rain or shine.
Heavy-duty fun for the entire family:
  • Activities, hands-on demonstrations and free giveaways.
  • Sit in the driver’s seat of a backhoe or dump truck.
  • See other machines used to dig trenches, haul rock, trim trees and more!

Tuesday, April 19, 2016

Let Us Know What You Think About Your Neighborhood!


The City of Tigard is asking residents to provide feedback on the features that make a neighborhood or city a great place to call home. Help your neighborhood by answering a few questions. Answers are completely anonymous. Results will be posted on the city’s webpage and shared with the Neighborhood Network blogs. Thank you!


Go here for the survey: https://www.surveymonkey.com/r/KF8S5J8
 

Thursday, March 31, 2016

Construction Update for Tigard, Week Starting March 30


Dartmouth Street and 78th Avenue Approaching Highway 99W
A contractor for Costco will be widening Dartmouth Street to add a new right turn lane as Dartmouth approaches Highway 99W and widening 78th Avenue to add a new right turn lane as 78th approaches Highway 99W.  Some traffic delays are possible.

Walnut Street (Tiedeman to 116th and intersection with 135th)
Walnut Street is under construction between 116th and Tiedeman to add sidewalks, bike lanes, a center turn lane, and underground utilities, and install a traffic signal in place of the all-way-stop at the intersection of Walnut St with 135th Ave.  Construction work is scheduled through May 2017, with a three-week closure in July/August 2016 to replace the culvert west of the Fowler tennis courts. 

95th Ave (north of Greenburg Rd) and North Dakota St (East of Greenburg Rd) Sidewalks
Construction is in progress on new sidewalks along 95th Ave north of Greenburg Rd and North Dakota St east of Greenburg Rd.  This will build ‘missing link’ sidewalks along two key neighborhood entrances, and will included an enhanced crossing of Greenburg Rd.  Construction is planned through May.

Bonita Road (Fanno Creek to I - 5)
The Water pipeline connection is complete under Bonita Road near Fanno Creek.  Traffic should be back to normal for a while until curb, sidewalk, and striping are replaced.

Main Street / Scoffins Street Intersection All-Way-Stop

The intersection of Main Street with Scoffins Street has been converted to all-way-stop traffic control.  This should improve safety, walkability, and traffic flow.  In this initial test phase the signal is operating in red-flash mode so the intersection functions as an all-way-stop.  If after a few months the intersection is indeed functioning better as an all-way-stop, the signal will be removed.  Comments and concerns can be directed to Mike McCarthy at 503-718-2462 or mikem@tigard-or.gov.


Ross Street / 81st Avenue Developments
Three private developments are under construction in the Ross/81st area: a) a large senior living center on the northeast corner of Ross and Hall which has opened new street connections of 83rd Ave with Matthew Park and Ross Street; b) a subdivision on the southwest corner of Ross and 81st; and c) a subdivision on the east side of 81st, each making half-street improvements along their street frontages.

Barrows Rd (154th to Roshak)
Clean Water Services, in conjunction with the cities of Tigard and Beaverton, is constructing a new 24” sewer line under Barrows Road (between 154th Ave and Roshak Rd).  Work includes construction of a new pipe in the roadway, with flaggers directing traffic and possible delays.  Construction is scheduled through April 2016.
 
River Terrace
River Terrace developments are under construction.  Earthwork and grading is in progress on a 137-lot subdivision and a 215-lot subdivision (both west of Roy Rogers Road just south of Scholls Ferry Road), and an 82-lot subdivision (west of 150th Avenue south of Bull Mountain Road).  Crews are building a sewer line under and making half-street improvements along 150th Ave. If you have any questions, please contact Mike White at 503-718-2464.
85th Ave (South of Durham Rd)
A contractor for Clean Water Services (CWS) has paved 85th Ave (the extension of Hall Blvd) south of Durham Rd and is building a new cul-de-sac just south of the business park.  CWS is shortening the public portion of 85th Ave to reduce traffic through its wastewater treatment plant area.  Walking and cycling access to the Cook Park trails will be maintained.

Durham Road and Upper Boones Ferry Road Signal Coordination
The city, county, and state are collecting traffic data for design of an updated signal coordination system for all of the traffic signals along Durham Road and Upper Boones Ferry Road from the Durham Rd / Hwy 99W intersection through the Upper Boones Ferry Rd / Interstate 5 / Carman Dr interchange.  Contact Mike McCarthy at mikem@tigard-or.gov or 503-718-2462 with any questions, ideas, or concerns.

Thursday, March 24, 2016

Want to Share Your Ideas on the Tigard Triangle?


The City of Tigard is working with a graduate student team from Portland State University (PSU) to explore walkability in the Tigard Triangle.


As part of their final project, these grad students need to hear from people who spend time in or with a strong connection to the Tigard Triangle.  The team from PSU is gathering community priorities on pedestrian conditions in the Triangle during a one-hour focus group Thursday, March 31. They want to hear from you about your priorities.

Please join us if you're able and pass along this invite to others who may be interested. Refreshments will be provided.
  • WHAT: Tigard Triangle Walkability Focus Group
  • WHEN: 5-6 p.m., Thursday, March 31
  • WHERE: Well & Good Coffee House, 7357 SW Beveland St, Tigard, OR
You can RSVP to davislin@pdx.edu, so we have an idea of attendance.

Your input will help this team create recommendations that can improve safety, walkability, boost small business investment, and livability in the Tigard Triangle.

Find out more about the project here: http://www.tigard-or.gov/value_of_place.php. Updates will be provided throughout the project -- including an additional short survey, an interactive community-created map of pedestrian needs, and information about a community focused planning workshop on April 20. You’ll hear more about these activities at the focus group meeting on March 31.

 

 

Wednesday, March 16, 2016

Tigard Walks Planned for Saturday, March 19


Get our your walking shoes and get ready to explore another corner of Tigard on Saturday, March 19. Details below.
Tigard Walks in March:
·         When: Saturday, March 19, 2016 @ 10 a.m.
·         Location: "What a View!” This route was suggested by a resident and if the weather cooperates, it offers stunning views of Mt. Hood and the city. It’s a hilly walk, but turn-by-turn instructions are included so you can find your way no matter what speed you’re walking.
·         Route MapSee the map
·         Don’t want to print a map?  Thanks to Tigard’s knowledgeable mapping staff, now there’s a link to access the map on your smart phone – open the link here and start your walk: Tigard Walks App
·         Questions? Please contact Joanne Bengtson at Joanne@tigard-or.gov or 503-718-2476.
Subscribe to this page and when updates are posted, you will be among the first to know. 


Happy trails!